The Challenge

The project faced multiple challenges, including budget pressures and an aggressive schedule that required construction to continue through harsh winter conditions. With a firm deadline to open the stadium for the Summit League Conference Championship, the team was under pressure to deliver despite unpredictable weather and design adjustments. Coordinating across trades and managing procurement timelines added to the complexity, all while maintaining a high standard for quality and performance.

Market

Higher Education

Project Scope

Construction Manager Advisor

Earthwork

3D Machine Grade Control Grading

Aggregate

Drainage

Synthetic turf installation

Fencing

Key Facts

Nemaha was brought onto the project early, allowing the team to influence scheduling, trade coordination, and material procurement from the outset.

The team assisted with design revisions to address budget overruns, ensuring the project stayed on schedule and within financial targets.

Nemaha secured a $180,000 Nebraska Recycled Tire Grant before project completion by proactively aligning the turf infill specifications with grant requirements.

Challenge Met

Nemaha’s early involvement, 14 months before field construction, proved invaluable in addressing these challenges. The team’s proactive role in schedule development, material procurement, trade coordination, and design review helped keep the project on track. When budget issues arose, Nemaha contributed to a rapid six-week redesign that maintained quality while aligning with financial goals. In a unique value-add, Nemaha identified and secured a $180,000 Nebraska Recycled Tire Grant for the owner by ensuring the turf infill met all necessary criteria. Their foresight and initiative brought funding to the project before construction was complete.